Thursday, October 2, 2014

Rinnai on demand hot water installation part 3

This is the third day for the hot water install. Today it took me 8 hrs to fit ,manufacture and  hook up 4 lines  then test them with soapy water for leeks. Way too long . The big problem was the 5/8 flar fittings that had to be made for the lines that got cut, input line ,in and output hot water lines and then the stove. Lucky joy is doing a double today so I can shut down the system.
Next is the hot and cold water, im not sure if i should move the accumulator closer to the new system ,but it would look a lot cleaner and 3 times more work .
The gas lines are now hooked up tested and not leaking. In terms of cost I just added another $100.00 to the parts charge and at least 4 more trips to home depot but that was my screw up for not knowing what i know now. Like BJ says ,you never stop learning
the gas loop

connetion into the house

to the stove
I'm going to move the accumulator over also but before that can be done all the water lines need to be run. I did some pricing and copper cost is so high that it wont be a good idea. I like the new PEX system, its much cheaper overall but the tools to do the job are very expensive. Since i plan to do the heating system also later I think its a good investment.

This assembly is going to be moved but I need to shut down the house and water for a day to do this.


 note the date on this old heater I think I got my moneys worth

Part 4 will be the new water lines but it will have to wait ,vie exceeded my current budget.